NO | SELECTED ACTIVITY | STANDARD CHARTER | ACHIEVEMENTS | ||||
JAN - MAR | APR - JUN |
JUL - SEP | OCT - DEC | ||||
1 | To organise at least 30 trade promotion activities every 3 months. | At least 30 activities every 3 months | 65 activities |
80 activities |
64 activities |
42 activities |
|
2 | i) | To entertain, answer and distribute information on trade opportunities within 4 working days. | Within 4 working days | 2,892 enquiries |
4,610 enquiries | 4,261 enquiries | 4,545 enquiries |
ii) | To disseminate international tender notices within 2 working days. | Within 2 working days | 10 notices |
36 notices | 22 notices | 20 notices | |
3 | To inform the results to the applicants for participation in the trade fairs and trade missions within one (1) week after the application closing date. | Within 1 week | 262 applications |
247 applications | 132 applications | 158 applications | |
4 |
To ensure the release of publications as follows: |
||||||
i) | MATRADE Online News - every 2 weeks | Every 2 weeks | 6 issues | 7 issues | 6 issues | 7 issues | |
ii) | MATRADE Leads - every week | Every week | 13 issues | 13 issues | 13 issues | 12 issues | |
iii) | Up-coming Events - every 3 months | Every 3 months | 1 issue | 1 issue | 1 issue | 1 issue | |
iv) | Trade Mart - every 2 months | Every 2 months | 2 issues | 2 issues | 1 issue | 2 issue | |
5 | To update the website within 2 working days upon receiving the updated information. | Within 2 working days | 52 information |
52 information | 41 information | 57 information |
|
6 | To review all completed Market Development Grant (MDG) applications and to give the results to the applicants within 10 working days. | Within 10 working days | 507 applications |
1,227 applications | 872 applications | 1,050 applications |